Ongoing Support despite Customer Delays

In 2018, Plant Werx provided PLC and SCADA automation services in our F&B customer’s facilities and utilities.

Goals
  • SCADA software version upgrade
  • Full deployment of migrated system
  • Decommissioning of old system
Challenges
  • Obsolete programming plugins from Windows XP era
  • The development part has been completed along with partial deployment in 2020 but customer encountered delays in other aspects of the project
Solutions Implemented by Plant Werx
  • Replacement of the obsolete plugins with built- in tools by AVEVA System Platform
  • As a reliable partner, Plant Werx is still following up with the customer about the progress and our engineer still attend to site concerns as and when necessary
Results
  • Easy maintenance of SCADA application on upcoming upgrades